Skip Navigation to main content U.S. Department of Energy U.S. Department of Energy Energy Efficiency and Renewable Energy
Bringing you a prosperous future where energy is clean, abundant, reliable, and affordable EERE Home
Wind & Hydropower Technologies Program
About the ProgramProgram AreasInformation ResourcesFinancial OpportunitiesTechnologiesDeploymentHome
Wind Powering America

 

EERE Information Center

News

Wind Powering America Update

June 11, 2008

New England Interview: Brian Fairbank, President and CEO, Jiminy Peak Mountain Resort

May 20, 2008

New DOE Report Analyzes a Path to Reaching 20% Wind Power by 2030

May 12, 2008

Ag Outreach Webcast: Wind Farming

May 8, 2008

Wind Powering America 2007 Activities Summary
(PDF 4.3 MB)
Download Adobe Reader

February 29, 2008

More News

Learn About Our RSS Feed Learn About Wind Powering America's RSS Feed

Subscribe to EERE News Updates

Events

National Association of State Energy Officials Annual Meeting

September 7, 2008

Utility Wind Integration Group Fall Technical Workshop

October 1, 2008

New Jersey Clean Energy Conference and Leadership Awards

October 17, 2008

More Events

Publications
An image of the cover of the Native American Wind Interest Group (NAWIG) Newsletter.

Native American Wind Interest Group (NAWIG) Newsletter
(PDF 1.3 MB)
Download Adobe Reader

May 6, 2008

Wind Powering Native America video cover

Video: Wind Powering Native America

January 1, 2004

More Publications

Features
Click on this installed capacity map to view a larger version.
What is Wind Power? Where is Wind Power? How do I get Wind Power? Wind for Kids Wind Photos Features graphic

Wind Powering America Home

About Wind Powering America

Program Areas
State Activities
Regional Activities
Agricultural Community
Native Americans
Anemometer Loan Program
Native American Wind Interest Group (NAWIG)Newsletter
Native American Case Studies
Native American Resources and Tools
Public Lands
Public Power
Schools
Small Wind
Economic Development
Policy
Siting Wind Turbines

Awards

Interviews

Resources and Tools
Anemometer Loans
Wind Maps
Videos
Audio
Publications
News
Events
Past Events


Wind Power for Browning, Montana Waste Water Treatment Facility

In late 1999, the town of Browning, Montana, and the Blackfeet Indian Tribe installed four Bergey Excel 10-kilowatt (kW) wind turbines adjacent to the town's sewage treatment plant. The turbines provided about one-quarter of the plant's electricity, displacing energy bought from the grid.

Location: Browning, Montana
Type of System: Grid-connected, distributed-generation
Project Status: The project formally extends through 2002.
Last Updated: 27 Feb 2001

PROJECT BACKGROUND AND OVERVIEW

The potential for wind energy development on Native American Reservations in the Great Plains has been discussed for the past 10-15 years. As part of the U.S. Department of Energy (DOE) Field Verification Project, the Blackfeet Tribe and the Town of Browning, Montana, received funding to install four Bergey Excel wind turbines to displace some of the electricity used at the Browning Waste Water Treatment Plant. To simplify matters, the project was so designed that practically all the energy produced was consumed on site, although the turbines were grid connected.

The potential for replication of this project is high. Many Native American communities have grid electrical loads that could be partially met with wind power. This project is subsequent to the Blackfeet 100-kW Wind Turbine Demonstration project. Currently, the Blackfeet have an agreement with SeaWest for a developing an additional 22.8-megawatt (MW) wind farm on tribal land. This project is part of an effort to encourage use of renewable energy resources found on many reservations.

Goals and Objectives

Displace grid electricity used at the Browning Waste Water Treatment Plant.

INSTITUTIONAL ASPECTS

Participants: Siyeh Development Corporation, Blackfeet Indian Housing, Town of Browning, Montana, DOE, National Renewable Energy Laboratory (NREL), Bergey WindPower Company.

Organizational Structure: Siyeh is in overall charge of the project. Responsibilities include coordination of the construction of the civil works, installation of the turbine, maintenance, and project documentation. Once the official 3-year project is completed, the turbines will become the property of the town of Browning.

Site Identification and Resource Assessment: Browning has a good wind resource. The site is adjacent to the waste water treatment plant. Because the project objective is to displace grid electricity, the site had to be near the treatment plant.

Installation: Siyeh coordinated the construction of the civil works. Bergey technician Peter Hubner supervised installation of the turbines.

Community Involvement: Local manpower was used to construct the civil works and install the turbine.

TECHNICAL CHARACTERISTICS

System Description (Components/Size/Brand/Number): 4 Bergey Excel/S 10-kW wind turbines on 100-ft towers

Technical Performance: The turbines have operated reliably during this project. Their installation involved a new type of inverter that initially had some teething problems. These problems were overcome, leading to a successful installation.

Provisions for monitoring and evaluation: A data acquisitions system (DAS) is in place for monitoring the turbines during the 3-year project period.

ECONOMIC AND FINANCIAL PROFILE

Financing Arrangements (Financing/Type/Rate of Return): This project was funded primarily with a DOE grant ($180,000 cash). Other project participants also made cash and in-kind contributions (Blackfeet Housing Authority, $25,000 cash; Town of Browning, $25,000 cash; Siyeh, $5,000 in-kind).

Cost recovery mechanisms and rates: All the electricity produced by this project is consumed by the waste water treatment plant. The system provides about one-quarter of the plant's usage.

LESSONS LEARNED

When the project manager resigned in the summer of 2000, the remaining project participants had difficulty keeping the project on track. This project has shown the dangers of allowing a project to depend too heavily upon one person. In the end, NREL technicians from Colorado had to be dispatched to assist with the DAS system.

AVAILABLE DOCUMENTATION

Electronic Archives:
Field Verification Program Web site

Published Articles:
Field Verification Program Quarterly Reports

CONTACT

Dennis Fitzpatrick
Siyeh development organization
P.O. Box 1989
Browning, MT 59417

 

 

Printable Version

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Skip footer navigation to end of page.